Payment Plan for Building Houses and Bungalows in Goa by Naik Construction, which is Hassle-Free Construction Experience, detailed Below:

We are delighted to offer our construction services for building houses and bungalows. Our team of experienced professionals ensures that we deliver high-quality construction services that exceed our clients' expectations.
Payment Plan for Building Houses and Bungalows in Goa by Naik Construction


In order to ensure a smooth and hassle-free construction process, we have devised a payment plan that requires clients to pay the full construction payment in several stages. This payment plan is designed to ensure that our clients only pay for the work in a Phase wise manner, before that stage of the Work only, reducing the risk of any financial disputes during the construction process.

The payment plan consists of nine stages, each of which corresponds to a specific phase of construction. Payments of each phase is to be prepaid. which ensures that we maintain transparency and accountability throughout the construction process.

The payment percentage for each stage ranges from 10% to 16%, depending on the complexity and scale of the work completed. This ensures that clients only pay for the work that has to be done and, thereby minimizing any financial risks and ensuring that our clients receive value for their money.

We understand that building a house or bungalow is a significant investment for our clients, and we are committed to delivering exceptional quality work that meets and exceeds their expectations. Our payment plan ensures that our clients have peace of mind throughout the construction process and can enjoy their newly constructed home without any financial worries.

So we are excited to offer our construction services for building houses and bungalows, and we believe our payment plan will provide our clients with a stress-free construction experience

We look forward to working with you and delivering exceptional quality work that will exceed your expectations.


INSTALLMENT STAGES For Residential (Ground + First floor) House Construction till plaster.

STAGE-I=10%: Work Description:-

  1. Footings Excavation in soft Soil (By JCB).

  2. Soling and PCC for footing (100mm each).

  3. Footing RCC Work.

STAGE-II=10% :Work Description:-

  1. Excavation for plinth wall in soft Soil.

  2. Soling and PCC below plinth Masonry (100mm each).

  3. Foundation Masonry (300mm undressed Laterite Stone).

  4. Column Casting from Footing till plinth beam bottom.

STAGE-III=10% Work Description:-

  1. RCC Plinth beam (400mm depth).

  2. Backfilling of Soil up to plinth level.

  3. Soling and PCC for rooms (100mm each)

STAGE-IV=10% Work Description:-

  1. Laterite stone masonry 230mm thick (230mm dressed Laterite Stone).

  2. Lintels, arches for doors and windows.

  3. RCC work of Columns till beam bottom level (after construction of walls).

STAGE-V=10% Work Description:-

  1. RCC work of Ground Floor Beam (500 mm depth) and Slab (120mm thick).

STAGE-VI=15% Work Description:-

  1. Fitting of Door and window Frames of Marti wood & M.S window grills Fitting.

  2. Internal and external plastering Work (internal single and external double coat). 

STAGE-VII=15% Work Description:-

  1. Laterite stone masonry 230mm thick (230mm dressed Laterite Stone).

  2. Lintels, arches for doors and windows.

  3. RCC work of Columns till beam bottom level (after construction of walls).

STAGE-VIII=10% Work Description:-

  1. RCC work of First Floor Beam (500 mm depth) and Slab (120mm thick).

STAGE-IX =10% Work Description:-


  1. Fitting of Door and window Frames of Marti wood & M.S window grills Fitting.

  2. Internal and external plastering Work of (internal single and external double coat).



Popular posts from this blog

Construction Civil Work Labour Rate Quotation Format Goa - 2023

Construction Price of Bungalow in Goa India(FAQ) (2023)

List of Document required for construction of house in goa